Preliminary Costs

Site setup and time-related costs including temporary facilities, site fencing, welfare units, scaffolding, cranes, and on-site project management staff. Preliminaries run for the duration of construction.

Why it matters

Longer build periods increase preliminary costs proportionally, creating a compounding effect on delays.